In August 2011 Linbrooke Services were approached and subsequently agreed to take over the relocation of Heaton Depot Signalling Panel for Network Rail and deliver it before the end of 2012.
This troubled project was originally awarded to Jarvis and then Clough Smith Rail with both companies going into administration before starting on site.
The project which has been planned
for seven years included :- 
· Signalling Design
· Telecomms Design
· Civil Engineering Design
· Signalling Correlation
· New Signalling Panel
· New Depot CCTV System, including columns
· Operational Telecomms Migration
· Cabling and Routeworks
· All Testing and Commissioning
· Recoveries and Handover Documentation
This is Linbrooke Services first Signalling project and demonstrates the company’s ability to successfully deliver multi disciplined contracts.